Hiser Builders Inc Is Using The Completed Contract Method For A 6 600 000 Contra
Hiser Builders, Inc. is using the completed-contract method for a $6,600,000 contract that will take two years to complete. Data at December 31, 2010, the end of the first year, are as follows:Costs incurred to date $2,560,000Estimated costs to complete 3,280,000Billings to date 2,400,000Collections to date 2,000,000The gross profit or loss that should be recognized for 2010 isAnswera.$120,000 loss.b.$105,600 loss.c.$240,000 loss.d.$0