for the given information kindly find the critical path and also help in calculating the project completion time
Work Q / Predecessors none / Duration 1 day
Work R / Predecessors Q / Duration 4 days
Work S / Predecessors Q / Duration 2 days
Work T / Predecessors Q / Duration 2 days
Work U / Predecessors T / Duration 3 days
Work V / Predecessors T / Duration 3 days
Work W / Predecessors U / Duration 2 days
Work X / Predecessors V,W / Duration 1 day
Work Y / Predecessors S,X / Duration 3 days
Work Z / Predecessors R / Duration 2 days
"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"
